Holcomb to grind and redo flaking track surface; timeline weather-dependent
Summary
Board was briefed on a warranty repair for the new track after the rubberized top layer began flaking; district and contractor plan to grind off the top layer and reapply material, with completion targeted for mid-February or mid-March depending on weather.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
District leaders reported that portions of the newly installed rubberized track surface were flaking and detaching in spots, and the contractor has indicated the work is warranty-covered.
"The rubberized paint, which is the final layer of the track, was flaking off," Dr. Myers said. The current working theory is an issue with surface cleaning prior to application; the district anticipates grinding off the top layer and reapplying material on a same-day cleaning-and-spray schedule. The superintendent said the contractor will perform the grinding within roughly 10 days and that plans A and B aim for mid-February or mid-March completion, weather permitting. A contingency plan would delay finishing until after track season, which could require moving or cancelling scheduled meets.
District staff will monitor the warranty and liquidated-damages timeline in the contract, and administrators are contacting nearby facilities in case meets must be relocated.