Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Economic Development topic

No spam. Unsubscribe anytime.

Council authorizes TIF letter of intent to spur Big Woods industrial park; staff frames aid as infrastructure reimbursement

Chaska City Council ยท July 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City and EDA authorized a letter of intent to pursue an eight-year TIF district to reimburse a developer for extensive public infrastructure needed to enable the Big Woods Business Park North; staff said the proposal supports a ~218,000 sq ft distribution facility and will be structured as pay-as-you-go reimbursement limited to public infrastructure costs.

The Chaska City Council and the City's Economic Development Authority authorized a letter of intent July 20 to pursue tax-increment financing (TIF) assistance to reimburse a developer for large upfront public-infrastructure costs at the Big Woods Business Park North.

City staff explained the proposed approach is not a subsidy for the private building itself but a mechanism to reimburse the developer for constructing public roads, utilities, mass grading and other site work that otherwise would prevent the park's northern parcels from becoming development-ready. Staff said phase one includes a roughly 218,000-square-foot distribution facility and that council-authorized LOI would create an eight-year economic development district and structure reimbursement as a pay-as-you-go arrangement.

Economic development staff and consultant Baker Tilly concluded the project has a financing gap because extensive public infrastructure must be built up front. Under the LOI framework the city would limit TIF reimbursement to public infrastructure, require a one-year lookback after project stabilization, and treat any support that exceeds initial policy thresholds as an "advanced investment" to be shared among future phases of the park.

Julie (city economic development staff) told the council the project would create new industrial employment and long-term tax base. Staff cited preliminary workforce estimates for the phase-one facility of about 200 full-time jobs at an average wage near $60,000 and additional logistics and distribution employment associated with the site; city staff said final TIF amounts and the TIF plan will be negotiated and brought back to council and the EDA for approval.

Council members voted to authorize the city administrator to execute the LOI and directed staff to continue negotiations and financial due diligence before returning a detailed TIF plan and agreement.