U-46 lists completion dates, ribbon-cuttings as summer construction progresses

Board of Education, School District U-46 · July 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District officials gave the board a multi-site facilities update, citing substantial-completion targets (Kimball July 31; Kenyon Woods Aug. 13; Legacy late fall) and a Sept. 9 groundbreaking for a new Elgin elementary school. Administrators said crews are prioritizing readying buildings for students under new attendance boundaries.

Board members heard an extended facilities and construction update on July 20 from district capital staff, who outlined timelines and milestone events across multiple projects.

Dr. Anne Williams, the district’s capital strategy and operations officer, said Kimball Middle School’s substantial completion date remains July 31 so furniture and cleaning can finish before staff return in mid-August and that a ribbon-cutting is scheduled Aug. 19. She said Kenyon Woods’ bus turnaround and site utilities should be complete in about two weeks with a planned ribbon-cutting Aug. 13. On Legacy Middle School she reported “over 100 trade people on-site” and said the project’s schedule calls for substantial completion in late fall so the building will be ready ahead of next school year. A new Elgin elementary being built on the former David C. Cook warehouse has ongoing demolition; the district scheduled a groundbreaking for Sept. 9 at 3:30 p.m.

Mr. Lindholm and other project leads reviewed progress at Century Oaks (mobile classroom connections and expected substantial completion in early August) and at Glenbrook (interior demolition nearly complete; staff and students will relocate to Hanover Countryside Elementary for the 2026–27 year). Project teams highlighted traffic improvements such as a turning lane on Rorsen Road intended to alleviate congestion and noted dust suppression and misting systems used during demolition at the David C. Cook site.

The board viewed a short video summarizing work across sites and had no substantive questions at the conclusion of the presentation. Administration emphasized that the schedules are intended to align with new attendance boundaries and the shift of sixth graders into middle schools.