Contractor: North Road drainage largely done; base paving likely week of June 16

Royalton Selectboard · June 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractor update: most drainage work is finished, headwalls expected next week, and the project is projected to reach substantial completion in mid-July. Staff warned the board of asphalt index exposure that could increase cost modestly.

The Royalton Selectboard heard a construction update from the project presenter about work on North Road, who said most of the drainage work — underdrain and cross culverts — is complete and that headwalls should be available next week. "We're hoping that the head walls will get put in next week ... the base course of pavement the week of the 16th," the presenter said.

The presenter told the board the team expects the wearing course and final touches by roughly the week of July 11, calling that the likely substantial-completion milestone. He also noted a budget sensitivity tied to the asphalt index and oil prices: "So it's probably around $10,000 ... that the asphalt is more expensive," he said, describing how state indexing of asphalt could affect the contract price. Chair (Speaker 4) and staff discussed using the schedule and daily field verifications to reconcile pay requests and to keep the job moving without unnecessary delays.

The presenter emphasized that the first base course is a critical milestone because it reduces erosion risk and allows easier progress toward final paving. The board and staff agreed to continue daily coordination and to copy the town point of contact on pay slips and daily reports to streamline reconciliation.