Keene public works seeks contractor quote to fix Lisa Carver Park ballfield; lighting installation slated for late August

Keene Economic Development Corporation (Type B) Board · July 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works presented a $16,880 contractor estimate to excavate and install a French drain in the Lisa Carver Park ballfield and said park lighting materials are expected mid-August with installation to follow in the third week of August.

Public works staff updated the board on planned improvements at Lisa Carver Park, including a contractor estimate of $16,880 to excavate one foot of the infield, install a French drain with corrugated pipe, add conditioned fill and make necessary connections to existing drainage. "About $16,880 to get that done just for the big field," a staff speaker said, and the contractor estimated they could start within a week and complete the field work in a few days once scheduled.

Staff also said the lighting project for the park is progressing: materials are projected to be delivered by mid-August with installation scheduled the following week (third week of August). The board discussed whether the ballfield work had been previously approved or allocated from that March’s $26,000 drainage approval; staff said some drainage work had been completed previously and that this contractor quote is for the remaining work. No formal vote occurred on contracting during the meeting; staff said they would use maintenance and repair funds or CIP budgeting as appropriate.