Board approves budget amendment on first reading to cover Anchor Green restroom cost overrun

Board of Mayor and Aldermen, Town of Farragut · July 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Farragut staff said the Anchor Green restroom project, originally budgeted at $400,000, requires an additional $49,912 to cover prior expenditures, a bid overrun of $8,150 and a contingency; Ordinance 26-16 was approved on first reading by roll call.

Town staff presented Ordinance 26-16 on July 23 to amend the fiscal year 2025-26 capital investment program fund to cover additional costs associated with the Anchor Green restroom project in the Biddle Farm Town Center area.

"The original budget for this project totaled $400,000," Chris Sheffield, director of public services, told the board. He said prior expenditures of $29,912 covered geotechnical and design services, the lowest construction bid exceeded the original budget by $8,150, and staff recommended adding an $11,850 contingency. To cover those amounts, staff proposed moving $49,912 from CIP reserves into CIP expenditures.

There were no public speakers on the item and no substantive questions from aldermen. The board held a roll call vote and approved Ordinance 26-16 on first reading; the mayor noted the approval occurred at approximately 6:13 p.m. on July 23, 2026. Staff said the amendment will allow the construction contract to proceed and provide a small contingency for change orders.