Council awards Jean Sweeney Aquatic Center contracts after bids show higher costs; project budget rises to $40.5M

City of Alameda City Council · July 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After receiving three qualified bids, Alameda's council authorized construction and professional-services contract amendments for the long-awaited Jean Sweeney Aquatic Center. Staff warned groundwater/dewatering and soil handling add risk and requested an additional appropriation that brings the project estimate to about $40.5 million.

The Alameda City Council unanimously approved three linked actions July 7 to move forward with the Jean Sweeney-area Aquatic Center: award the primary construction contract to Wickman Construction (base + contingency), amend the project manager contract (Griffin) and increase the ELS Architects agreement for preliminary design work. Recreation & Parks Director Justin Long summarized a lengthy procurement and prequalification process, explained geotechnical and groundwater constraints on the Jean Sweeney site, and recommended a $3 million construction contingency to address dewatering/soil uncertainties required by DTSC supervision.

Long said a base-construction estimate prepared in an earlier phase had been $25.35 million but current bids and required ground-improvement work raised the realistic construction cost; the staff package requested a project total of about $40.5 million including soft costs and a $3 million construction contingency. The project includes a 30-meter competition pool, activity pool, locker rooms and an electrified mechanical system; AMP offered a rebate toward electrification. Long projected the full-service facility would require an operating subsidy initially (staff estimated roughly $400,000/year) but would substantially expand year-round public programming and swim lessons that the city currently shares with the school district.