Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Facilities Construction topic

No spam. Unsubscribe anytime.

Owner's representative reports progress at Wanamaker, Pauling South and Auburn; structural steel delay noted

Board of Education · April 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Tucker, the owner's representative, briefed the board on ongoing renovations at Wanamaker, Pauling South and Auburn, reporting reroofing and HVAC timelines, demo of collaboration spaces, a non-critical delay in structural steel delivery, and plans for a late-June budget reconciliation and warranty tracking.

Tucker, the owner’s representative, told the board crews have been reroofing Wanamaker since spring, are installing sheetrock and expect HVAC units to start by the end of the month. He described similar renovation work at Pauling South and Auburn (demo of collaboration spaces and phased summer work) and said the team is keeping an eye on a non-critical structural-steel delivery delay.

Tucker also said the district will perform a construction-budget reconciliation in late June to assess remaining soft costs and contingency usage, and staff are documenting warranty and punch-list items as projects approach their one-year warranty windows. He said project meeting frequency will increase—likely to weekly—after June to stay on schedule.