Council approves $307,176 pay application for treatment-plant work, tables exterior-painting decision

Milford Town Council · May 31, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Milford council approved a $307,175.71 pay application for interior build-out work at the wastewater treatment plant and tabled a $20,580 exterior painting change order until rooftop-access costs are determined.

The Milford Town Council voted to approve Division A pay application No. 9 for the wastewater treatment plant, authorizing payment of $307,175.71 to cover interior work including plumbing and electrical. Ryan Brian LaRue presented the application and recommended the payment, saying, “This pay application is in the amount of $307,175.71.”

Councilors discussed a separate change order (Change Order No. 1) for exterior coating and painting of the treatment plant, presented at $20,580. LaRue said the coating would largely be aesthetic with added weatherproofing and could be done concurrently with interior painting. Council members agreed they needed rooftop-access pricing before deciding and voted to table the change order until those numbers are available. Chair called for the item to be prioritized with the contractor so a rooftop-access estimate will be available before the next meeting.