Florence approves pay requests and a $60,298 change order for Eagle Post Road/sewer projects
Summary
The board approved Pay Request #2 to A.J. Construction for $60,116.03 and Pay Request #1 to Thornton Construction for $131,230.53, and authorized a $60,298.67 change order for Thornton on the Hwy. 49 Eagle Post Road sanitary sewer project.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
City Engineer Tim Parker presented multiple construction payments and a contract change order during the Oct. 7 meeting. The board approved Pay Request #2 from A.J. Construction for $60,116.03 related to the Eagle Post Road overlay LPA project, and Pay Request #1 from Thornton Construction Company, Inc. for $131,230.53 for MCWI #255-2-CW Hwy. 49 Eagle Post Road sanitary sewer additions Phase 3 and the College Street pump station force main replacement.
The board also approved Thornton Construction Company, Inc. Contract Change Order No. 1 in the amount of $60,298.67 for MCWI #1255-CW-5.5 Hwy. 49 Eagle Post Road sanitary sewer additions Phase 3. Alderman Grantham moved approval of the pay request and Alderman Sistrunk seconded; votes were unanimous among members present. Alderman Herrin temporarily left the meeting and later returned but did not participate while absent.
These approvals advance ongoing road and sewer infrastructure projects; the minutes list amounts and project identifiers but do not include contractor schedules, funding sources, or the detailed justification for the change order.