Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Florence approves $727,150.53 in infrastructure pay requests, directs MDOT coordination

Mayor and Board of the City of Florence · July 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Pay Request #8 to Hemphill Construction for $20,200 and Pay Request #1 to A. J. Construction for $706,950.53, and authorized the city engineer to coordinate with MDOT on Hwy. 469 turn‑lane timing for the Cal‑Mar project.

City Engineer Tim Parker presented construction pay requests and a coordination item July 15. The board approved Pay Request #8 to Hemphill Construction Company, Inc. in the amount of $20,200.00 for the Hwy. 49–Eagle Post Road Sanitary Sewer Additions Phase II Project, and approved Pay Request #1 to A. J. Construction, Inc. for the Eagle Post Road Overlay Project in the amount of $706,950.53.

Separately, the board authorized and directed City Engineer Tim Parker to work with the Mississippi Department of Transportation regarding the timing of Hwy. 469 widening tied to a turn lane for the Cal‑Mar Project. All motions carried unanimously, and the minutes record the pay amounts and project identifiers as noted.