Board approves $78,928.62 increase to Hwy 49 Eagle Post Road sewer contract
Summary
The Florence board unanimously approved MCWI change order #4 increasing the contract for Hwy 49 Eagle Post Road sanitary sewer additions—Phase II by $78,928.62; Alderman Herrin left the meeting during earlier discussion and was later invited to rejoin without participating in the vote.
Get email alerts on the Sanitary Sewer topic
No spam. Unsubscribe anytime.
City Engineer Tim Parker recommended approval of MCWI change order #4 to increase the contract for the Hwy 49 Eagle Post Road sanitary sewer additions—Phase II by $78,928.62. Alderman John Banks moved the change order; Alderman Kyle Martin seconded and the motion carried unanimously.
The minutes record that Alderman Mason Herrin left the meeting during discussion and was invited to return, with a note that he had not participated or deliberated on the item while absent. The record does not include a line-item explanation of the reason for the cost increase or a revised project completion date.