Engineer reports Phase IV sewer nearly complete; Phase V on hold; Route 20 bids scheduled
Summary
The engineer reported Phase IV sewer line work is complete with about 45 days of concrete and sidewalk work remaining; Phase V is on hold. A Route 20 Corridor bid opening is set for Oct. 9, 2024; AML Phase I closeout and Phase II NEPA assessment are underway.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Town engineering staff reported that Phase IV sewer line work is complete and that the contractor has approximately 45 days of concrete and sidewalk work remaining; the Sandy’s Hardware force main is being added into the contract. Phase V sewer work remains on hold.
The Route 20 Corridor prebid meeting took place on Sept. 18, 2024 and a bid opening is scheduled for Oct. 9, 2024 at 12 p.m. at the Thrasher office. AML Phase I closeout work continues with a forthcoming Change Order 3 for additional paving and screening; the Phase II AMD NEPA environmental assessment has been drafted and is in submission process.