Council approves $21,710 increase to contractor pay to finish street-improvement sections

City of Montrose City Council · September 10, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city engineer asked council to approve a $21,710 increase to a contractor's price for two sections of the 2024 street-improvement project due to lost supplier discounts after the award of other sections; the council approved the increase 5-0.

The city engineer told the council that awarding only sections B and D reduced the contract volume and caused supplier discounts to disappear, and the contractor requested an additional $21,710 to make the fall work feasible. Staff recommended approving the increase rather than rebidding and risking further delays or higher bids next year.

Councilors discussed the trade-offs — higher immediate cost vs. the risk of rebidding and project delay — and a motion to accept the $21,710 increase was made, seconded, and passed unanimously (5-0). Staff said the contractor indicated they would perform the work this fall if the council approved the increase and that a contract signature would follow.