Water commission reports Tank 1 state approval; pump option could free allocations for new lots

Chimney Hill Owners Association, Inc. Board of Directors · February 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Steve Boyce told the Chimney Hill board Feb. 15 that Tank 1 has state approval and can be placed into service; the water commission is also asking the state engineer for more information on a pipe-bursting proposal and is considering adding a redundant pump at Tank 3 to allow more lot allocations this summer.

Water Commission member Steve Boyce reported Feb. 15 that Tank 1 has received state approval and is ready to be placed into service for the Chimney Hill water system.

Boyce said a new state engineer is reviewing additional documentation on the association’s pipe-bursting proposal and that the commission is exploring an alternative solution: installing a redundant pump at Tank 3. He said the redundant pump could increase water allocations for additional lots and that the commission hopes to have the pump installed this spring to permit lot allocations this summer.

The board recorded the report as part of management updates and noted the water project remains in progress; any allocation increases would be contingent on state approvals and final engineering work.