Board hears update on pump redesign, generator RFPs and permit work for Chimney Hill water system

Chimney Hill Owners Association, Inc. Board of Directors ยท March 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The water commission reported that pump design work (Tank 3 to Tank 2), a supply/demand chart to support state allocations, generator RFPs for tank and well sites, and B tank design proposals are underway; pipe bursting is paused pending state comments.

Steve Boyce presented the water commission update: James Walker and staff have drafted a design for new transfer pumps from Tank 3 to Tank 2 and prepared an updated supply/demand chart that the minutes say "shows the impact of upgrades, which will allow the state to release more water allocations." The board is collecting electrical-work quotes and James Walker is assembling requests for proposals for site generators and B tank design and construction.

Board members noted pipe bursting work is on hold pending state review of permit comments. The board discussed next steps for permitting and budgeting; earlier in the meeting members signaled intent to direct remaining year-end funds toward water projects and the capital reserve plan supports projected 2025/2026 projects.