Commissioners approve vendor payments, grant filings and multiple contracts totaling key county investments
Summary
The board approved $1,274,401.89 in vendor payments, acknowledged VOCA/SVAA filings for victim services, authorized advertising for a generator replacement project, approved SCADA contract awards (estimated $125,000 per vendor annually) and accepted an OPWC $1,000,000 grant authorization for a Chapel Road water-main project, among other routine contract and settlement actions.
Get email alerts on the Finance topic
No spam. Unsubscribe anytime.
At the July 22 meeting the Clermont County Board of Commissioners approved a slate of financial and contract items, including a resolution to pay vendors $1,274,401.89, grant application acknowledgements and multiple procurement actions.
The board adopted Resolution No. 115-26 to approve vendor payments totaling $1,274,401.89 for checks dated 07/22/2026. A prosecutor's-office representative acknowledged electronic filings for the VOCA and State Victims Assistance grant applications to continue advocate services through 09/30/2027; the representative provided grant totals and match figures during the reading. The board also authorized a Purina Foundation grant submission by Job & Family Services to support a wraparound program partnering with Pressley Ridge, the Clermont Animal Shelter and Interparish Ministry Food Pantry, with awards reported in the $10,000–$50,000 range and no local match required.
On procurement, the board authorized advertising for bids to replace the Grama Tower generator in Bethel with bids due 08/27/2026; it approved awarding SCADA systems-integration and support contracts to specified vendors at an estimated annual amount of $125,000 per vendor for a three-year term; and it approved executing an OPWC project agreement (CJ04AD) authorizing a $1,000,000 grant for Chapel Road water-main replacement while noting the county share of the project cost. Several project change orders and a final payment for MGS water treatment plant construction (release of retainage and principal $8,820.40) were also approved by roll call.