Authority flags Wesson Canal pump failure; emergency replacement may be needed
Summary
Staff reported a failure at the Wesson Canal pump station that left one of two pumps inoperable; the vendor indicated parts are discontinued and recommended replacing the pump drive and controls with an early cost estimate of about $150,000 and possible emergency procurement.
Get email alerts on the Infrastructure Failure topic
No spam. Unsubscribe anytime.
During the project updates, staff reported a recent failure at the Wesson Canal pump station that rendered one of two pumps out of service. A vendor assessment found the failed parts are no longer manufactured and recommended replacement of the pump drive and control systems.
Executive Director Joe Danielson described the situation as emergent because operating on a single pump raises the risk of overflow if the remaining unit fails. He said the authority is seeking a vendor quote and estimated, "we're taking a blind guess thinking it's going to be $150,000," noting staff may pursue an emergency purchase to shorten procurement timelines and secure the necessary parts. "Right now, we're working on—we only have 1 working pump out of 2. If that goes down, we would have to go on bypass so we don't have sewage overflowing and running down the street," he added.
Staff said they will request a formal quote from the vendor and present emergency purchase paperwork to the board if required. The authority plans to warehouse salvageable parts and coordinate procurement steps with counsel and engineering staff to expedite repairs.