Board approves up to $15,000 change order for irrigation repairs tied to drainage project
Summary
District engineer presented a revised Seaside & Master Drainage Project scope and ancillary irrigation repair costs; the board approved an Irrigation Concepts change order not-to-exceed $15,000 to fix wiring and raise irrigation heads.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
District Engineer Charlie Krebs presented a revised scope for the Seaside & Master Drainage Project intended to preserve the project's original intent while making it easier for operations staff to make adjustments. MRI expects work to begin within two to three weeks.
Mr. Krebs reported ancillary irrigation costs from Irrigation Concepts: $4,002.50 to repair damaged wiring and about $1,300 each to raise seven to eight irrigation heads. The board approved the Irrigation Concepts change order to repair damaged wiring and raise seven to eight irrigation heads in a not-to-exceed amount of $15,000 (motion by Mr. Blumenthal, second by Mr. Schultz, with all in favor).
Staff will proceed with the drainage contract work and coordinate irrigation repairs under the approved change order and report back on scope and expenditures.