Board hears Tank 1 repair update and pipeline permit follow‑up
Summary
The Water Commission reported Tank 1 was patched and a leak‑test certification is scheduled; staff follow up with the State on pipeline replacement permits and Well 15 tie‑in, and a Tank 1 tour was planned after the meeting.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Steve Boyce told the Board that Tank 1 was patched following last month’s engineer report and that a leak‑test certification is scheduled. Two employees are now eligible for water operator licenses, the commission reported.
Executive Director James Walker said he is continuing to follow up with the State on permits for the pipeline replacement and the Well 15 tie‑in. The Board arranged a tour of Tank 1 after the meeting to review progress in person.