Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Parks Capital Projects topic

No spam. Unsubscribe anytime.

SECO project lead says ball fields on track to open April 2026, tennis complex in fall 2026

Park It / Community Updates · November 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Aaron Stewart reports the SECO ball fields project has turf down on four fields, a center structure with concessions and a view deck in place, ongoing work on irrigation and sod, and target openings of April 2026 for the ball fields and fall 2026 for the tennis complex; he said the project remains on schedule and on budget.

Aaron Stewart offered a construction update from the SECO site, reporting visible progress across the project footprint. He said turf has been installed on all four fields and personnel are laying infill; a center building housing concessions, a flex room and restrooms — with a view deck on top — is built; lighting systems, dugouts and fencing are nearing completion; and crews are installing irrigation for a natural sod outfield with sod to be laid in the coming weeks.

“We’re remaining on time and on budget,” Stewart said. He gave schedule targets of April 2026 for opening the ball field complex and fall 2026 for opening the tennis complex, noting that tennis demolition occurred earlier in the project and that site work for the tennis phase will increase in the coming months. Stewart also said the warm-up area is in place and other finishing work remains as crews complete final systems and landscaping.

Stewart described the timeline and immediate next steps at the site, including completing irrigation and laying sod for the natural outfield. He framed the update as a progress report and said another update would be provided in the future.