Mayor outlines delays, disputes and $41,000 in right-of-way costs on Cedar waterline project
Summary
The mayor said the Cedar waterline project to the wastewater plant was significantly delayed by undisclosed nearby utility lines and difficulty getting a railroad inspector, and reported the city experienced $41,000 in additional right-of-way costs while KLJ and COP discuss additional charges.
Get email alerts on the Infrastructure Project Management topic
No spam. Unsubscribe anytime.
The mayor updated council on delays and additional costs related to the Cedar waterline that serves the wastewater plant, saying the job "started out as a relatively simple job" but became complicated because of undisclosed nearby lines and railroad inspection scheduling problems.
He said the city experienced roughly $41,000 in additional right-of-way costs and that conversations are ongoing between the consultant (KLJ) and the contractor (COP) about other additional costs. "We had issues with getting the railroad inspector in here that caused delays," the mayor said, and staff will prepare a report to give council more detail and to outline any funding requests that may follow.
Council members were told to expect further information and potential requests for funding once the report and cost reconciliation with contractors are complete.