Lakeland approves $131,530 net increase for North Side pump station after multiple change orders
Summary
Commission authorized several change orders to a June 2023 Felix Associates construction contract for a North Side pump station, resulting in a net additional city cost of about $131,530 after contractor cost-sharing and reimbursements.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Staff outlined four change orders to the Felix Associates construction contract for the North Side pump station, originally awarded at $7,231,750 with construction beginning in December 2023. Change orders included an EPA-required refrigerant update (≈$5,000), significant site-condition work including an old manhole replacement and drainage additions ($292,026), split design/construction error costs ($90,000, to be split between contractors), and removal of an undocumented abandoned 18-inch force main (~$47,606).
After pass-through reimbursements and contractor cost-sharing, staff reported the additional net impact to the city is approximately $131,530 and asked the commission to authorize an increase to the purchase order. Commissioners approved the change orders on a voice vote. Staff explained the change-order process and noted a shift toward including contingency amounts in future contracts to reduce the need to return to the commission for incremental change-order approvals.