Lakeland approves design contract for Beacon Hill water-main replacement; staff flags lead-pipe findings
Summary
Commission authorized Jones Edmunds for design services to replace roughly 11,000 feet of aging water main in Beacon Hill, with base design capped at $218,000 and potential construction-phase services raising the task authorization to about $421,000; staff cited citizen reports and spot lead piping discoveries.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The commission approved a task authorization authorizing Jones Edmunds and Associates to design replacement of approximately 11,000 feet of water mains in the Beacon Hill community. The base design scope is not to exceed $218,000; optional construction-phase services and contingencies could bring the total task authorization to about $421,000, according to staff.
Matt Fowler, Water Utilities Engineering Manager, told commissioners the design is expected to take about six months and construction "less than 1 year to install" depending on conflicts found during field investigations. The project follows citizen reports that led staff to discover aging and some lead gooseneck connections in places; staff said the work will also add hydrants to improve fire protection in the area.