P3: $322 million paid to developer so far, advanced payments account for $199 million

Metro Flood Diversion Authority · July 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The P3 representative said the authority has paid about $322,000,000 to the developer to date, including roughly $199,000,000 in Series A advance payments and additional interim and milestone payments.

The board heard a summary of payments made under the public‑private partnership. "We've paid about $322,000,000 to the developer to date," P3 representative Bakkegard told the board, adding that roughly "$199,000,000" came from Series A advance payments. He said interim completion (ICE) payments and statement‑of‑principles payments accounted for other notable sums and that a $5,000,000 milestone payment was recently triggered by completion of interstate bridges.

Bakkegard described remaining contingency and developer change items and noted the authority maintains a weekly standing committee to review interim completions and advance payments. Board members asked routine questions about payment oversight; staff said those processes would continue and be tracked closely in coming months.