Board debates upsizing planned 12" town mainline to 16"; asks for cost breakout
Summary
Board discussed converting a planned 12" mainline upgrade to 16" to increase future flow (est. 750k–1,000k gpd difference). Dusty provided a rough $4,000,000 materials estimate and recommended staging the project; board asked staff for a clear price breakdown and staged plan before deciding.
Get email alerts on the Mainline Upgrade topic
No spam. Unsubscribe anytime.
The board reviewed a planned 12-inch mainline replacement through town and a proposal to upsize to 16 inches to increase future capacity.
Dusty Paint summarized early estimates: “He said for the whole job is guest amount about 4,000,000... That that's his guess,” and noted his materials estimate and that engineering and labor were not included in that rough figure. Board members emphasized that the state highway department would cover costs for the 12" portion installed as part of highway work, but the district would be responsible for any delta to upgrade to 16".
Members asked for a staged approach — likely plant-to-highway first — and requested that staff obtain a firm, itemized price from David and a materials-only comparison between 12" and 16" so the board can evaluate the net cost the district would bear. Dusty said he will seek engineering pricing and grant opportunities; the board took no action and tabled the decision pending specific cost breakdowns.
The discussion also included ISO-related infrastructure (flush plugs) and the potential insurance savings for members if ISO ratings improve. The board directed staff to return with numbers and a plan at the next meeting.