Board approves Welcing Street mill-and-overlay and awards North Jefferson contract to low bidder

Village of Bonduel Village Board · May 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved a mill-and-overlay for Welcing Street and awarded the North Jefferson Street contract to MCC, Inc., the low bidder at $61,547.88 plus a 10% contingency; both motions passed unanimously.

Director Rankin presented quotes for Welcing Street (by the Public Safety Building) and recommended using budgeted Street Maintenance Contracted Services funds for a mill-and-overlay this year rather than performing crack sealing. The Board introduced and approved Resolution 2025-09 to proceed with the mill-and-overlay; Trustee Pleshek moved the resolution and Trustee Zuleger seconded. Rankin noted the Wolf River Asphalt & Sealcoating bid included the mill-and-overlay while other bids proposed only a tack coat.

For North Jefferson Street the Board opened bids on May 6; MCC, Inc. was the low bidder with a base bid of $61,547.88. Rueckert-Mielke reviewed the bids and raised no objections to MCC. The Board introduced and approved Resolution 2025-10 to award the North Jefferson Street contract to MCC, Inc., with an added 10% contingency for unpredictable project costs. Both measures passed by unanimous roll-call votes recorded in the minutes.