Chadron council approves change order and $131,862 payment for Cedar Buttes sewer project

The Mayor and City Council of the City of Chadron, Nebraska · July 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order No. 1 (+$1,842) for the Cedar Buttes Sanitary Sewer Extension District No. 71 and authorized payment to Buettner Construction for the current contract amount of $131,862.00; staff said reconnection work was needed due to an existing service entering the work area.

The City Council on July 6 approved a $1,842 change order to Buettner Construction for the Cedar Buttes Sanitary Sewer Extension District No. 71 and authorized Contractor's Application for Payment No. 1 for the full current contract amount of $131,862.00.

Utilities Superintendent Torey Zuver explained that during installation crews encountered an existing sanitary sewer service from Royal Court that entered the manhole where the new main was being placed; the service had to be disconnected and reconnected to the new main, which produced Change Order No. 1 dated May 27, 2026. Planning/Building/Zoning Official Janet Johnson added that staff has already received development inquiries for the area and intends to propose a sanitary sewer tap fee at a future meeting.