Contract update: Chadron Library renovation shows $467,300 current total; $28,437.68 certified for payment

Chadron Public Library Board of Directors · July 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Documents reviewed at the July 17 emergency meeting show the Chadron Library renovation original contract at $449,650.00 with $17,650.00 in approved change orders (current contract $467,300.00). The contractor's Application #1 certified $28,437.68 for payment after retainage.

Board members reviewed Fuller Construction's Application #1 for the Chadron Library Renovation at the July 17 emergency meeting. The application lists an original contract amount of $449,650.00 and approved change orders totaling $17,650.00, producing a current contract amount of $467,300.00. The document reports total completed and stored of $29,934.40, retainage of $1,496.72, and a certified payment amount of $28,437.68 for the period through June 30, 2026.

The application also shows a balance to completion of $438,862.32. These figures were provided in the contractor's documentation presented to the board; the board moved to approve the certified payment during the emergency session. Board President Heather Crofutt prefaced the meeting by reading the statutory open-meetings notice: "As required by Section 84-1412, subsection of the Nebraska Statutes, notice is hereby given that a copy of the open meetings act is posted for your examination." The record does not specify funding sources for the contract or additional payment conditions.