District updates: bus garage and home field house near completion; band tower footings underway
Summary
Construction contractor updates showed the new bus garage exterior and interior work progressing (brick, HVAC and slab pours), the field house finishing interior fixtures and concession areas, and band tower footings being excavated this week with no obstacles reported to using the facilities next school year.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
A project representative (voice 3) showed photos and described progress on capital projects: the bus garage brick façade and metaltrim are nearly complete, HVAC units are in place and slab pours for pits and aprons are scheduled depending on weather; interior mezzanine stairs and eye wash stations were installed. "This is the interior. You can see a lot of stuff is already in place," the representative said while walking through photos.
The home field house exterior steel was color matched and interior showers and concession areas were shown; the band tower footer was being dug this week and progress meetings do not foresee obstacles to the band using the facility next year. The board acknowledged the updates and thanked project staff; no contract awards or change orders were acted on at this meeting.