Council approves South Main Street waterline bid to Flowline Construction for $349,885.78 with $35,000 contingency
Summary
Council awarded the South Main Street waterline replacement to Flowline Construction for $349,885.78 and approved increasing the contingency to $35,000; staff said the work will draw on remaining ARPA funds and water-reserve funds and is scheduled to begin between Oct. 9 and Dec. 15 with 75 days for substantial completion.
Get email alerts on the Infrastructure Water topic
No spam. Unsubscribe anytime.
The council voted to award the South Main Street waterline replacement to Flowline Construction in the amount of $349,885.78 and agreed to increase the contingency to $35,000 after discussion about potential change-order risk and use of remaining ARPA funds. City staff said the project replaces approximately 854 feet of aging 8-inch cast iron pipe between 115 and 423 South Main Street because of repeated failures and repairs; Westech Engineering recommended the low bid for award.
Staff told the council the project will start no earlier than Oct. 9 but no later than Dec. 15 and will allow 75 days for substantial completion. Councilors discussed raising contingency from 5% to 10% so change orders would not force a return to council; the motion ultimately set the contingency at $35,000. Staff also explained that using ARPA funds for the project could reduce money available for small community projects (a basketball court, a generator, and 3D printers), and that any additional appropriation beyond the contingency would require a supplemental budget or transfer resolution.