Final pay application and credit approved for Boyne City 2024 streets project, lowering total cost
Summary
The commission approved a change order reducing the 2024 streets contract and authorized final payment after credits, lowering the project total by roughly $48,832 and finalizing payment to the contractor.
Get email alerts on the Street Projects topic
No spam. Unsubscribe anytime.
Public works staff reported that the 2024 Streets project—originally let to a contractor for multiple streets—has reached final accounting. Change Order 2 will reduce the contract by $48,832; Pay Application 3 will release retainage and pay $35,979.75 to the contractor, bringing the final project cost to about $680,006.82.
Staff described the usual balancing of quantities and punch‑list items used to calculate final credits and retainage. Commissioners thanked staff for pursuing credits and finalizing the project’s closeout.
The motion authorizing the change order and processing the final pay application passed by roll call.
Next steps: Staff will process the final payment and close out project records.