Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Site Progress topic

No spam. Unsubscribe anytime.

Project team reports slabs in place, framing nearly complete; weather‑tight goal targeted Sept. 1

Town of Northborough 5‑Station Building Committee · July 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Presenter reported all three main slabs are in and administration exterior framing is about 90% complete; the project team says weather‑tight status is being tracked toward an expected September 1 milestone while commissioning and performance testing will follow.

Presenter (Speaker 6) described visible site progress: "the slab all 3 slabs are in" (apparatus slab, administration slab on grade and second‑floor slab on deck) and said exterior administration wall framing is roughly 90% complete. Masonry work and waterproofing are scheduled to follow exterior sheathing and roofing in the next weeks.

Staff member (Speaker 1) outlined the commissioning sequence, saying substantial completion results in an occupancy permit and operational equipment but that final completion may occur up to about 60 days after substantial completion; performance testing of mechanical systems (heating and cooling) will be staged and may wait for suitable weather for cooling tests. The project team said it is tracking a weather‑tight milestone expected to be ready by September 1.