Director Squire updated the council on the South Second East water project and a Main Street bore: the main line is in and pressure testing has begun, crews will install pipe through Main Street next week, and the south side of town is experiencing reduced pressure and potential short-term water shutoffs to repair leaks; the city applied 2,400 gallons of mag chloride to industrial park roads.

Director Squire told the council the South Second East project is progressing and that the main line is in place and pressure testing is underway on the first block. He said crews will start service connections in the next few days and then shift work to install pipe through Main Street where a bore has already been completed but pipes still need to be placed.

Squire warned that work has temporarily reduced pressure on the south side of the city and that some residents may completely lose water when crews shut service to repair leaks on Second South; he said the contractor will shift crews to address fire-protection concerns and expects Main Street work to last "days, a week at least." Council members asked clarifying questions about the scope and timing of asphalt replacement and concurrent work on other roads.

The director also said the county applied about 2,400 gallons of mag chloride on city gravel roads in the industrial park and will bill the city for the material; he reported the leak under the tracks had been addressed and discussed planned cemetery water-meter work.