Resident Calls Out 18‑Month Delay in Public Notice, Warns Ratepayers Will Bear Costs
Summary
A Nellysford resident told the joint meeting that residents learned about plant problems too late and warned that proposed fixes and recent county spending will fall to ratepayers, pressing boards for transparency and accountability.
Get email alerts on the Public Comment topic
No spam. Unsubscribe anytime.
Stephen Bayne of Nellysford used the public comment period to criticize what he called insufficient transparency and delayed disclosure about the Wintergreen plant problems. Bayne, who described reviewing an "shocking executive summary," said residents living near Pond Hollow Creek and the South Fork of the Rockfish River were not informed for 18 months that they may have been at risk and that a pending July 21 public hearing on rate increases will shift costs to ratepayers.
Bayne urged the boards to pursue financial contributions and accountability from Ovivo, engineers, and the contractor, saying, "after 20 months of issues, no one should find this situation acceptable." The boards allowed the comment and then moved back into director discussion; supervisors reiterated expectations for more timely reporting and documentation of outreach to responsible parties.