Town highway official outlines milling and paving schedule for Farmington in early August
Summary
Farmington highway staff told the planning board they intend to mill Stonefield Estate, Chelsea Place and parts of Colette Road July 27–29 and to pave those streets during the first two full weeks of August (Aug. 3–6 and Aug. 10–13); additional work on Colette from County Road 8 to 28 is also planned.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The town highway official reported a multi-day milling and paving sequence for residential roads in Farmington. The team plans to mill Stonefield Estate, Chelsea Place and sections of Colette Road July 27–29 (two-day target per location), then pave the streets during the weeks of Aug. 3–6 and Aug. 10–13. Work on Colette Road from County Road 8 to 28 is also scheduled.
The official said crews will attempt to complete each location in two days and asked for public patience while work is scheduled; timing is tentative and depends on coordination and weather. The board heard the schedule during the open-discussion portion of its July 20 meeting and accepted the highway update as part of town operations planning.