Sewer lining resolves gym-floor backups; board backs low boiler bid for architect review
Summary
City staff reported the sewer lining outside the Public Safety Building resolved prior backups and protected the gym floor. The board recommended a low bid of $124,970 from Glady Plumbing and Piping to city council, pending architect review, with a board vote recording six ayes and one abstention.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Staff reported that a contractor completed lining of the sewer line outside the Public Safety Building and that subsequent checks found no backups or water on the gym floor.
"There was no backups in that manhole. There was no water on the gym floor," the superintendent reported, and staff said the additional lining work—outside the building though not in the original scope—was important to prevent recurring interior problems.
On a related facilities item, the board reviewed bids for a boiler replacement at the building. Three bids were submitted; staff reported the apparent low bidder as Glady Plumbing and Piping at $124,970, with the second-lowest bid at $132,960. The board moved to recommend the low bid to city council subject to architect review; the roll call recorded six ayes, zero nays and one abstention.
The chair noted the boiler work is budgeted from the ESU capital appropriation previously discussed and will appear on the August city council agenda for final action.