Smoke testing finds 102 defects; ESU plans televising and targeted repairs in Basin 4 and Basin 9
Summary
Staff reported 102 defects discovered during smoke testing in Basin 4 (south of town) and ongoing work in Basin 9 (northeast). Groundwater infiltration and storm inlets tied to sanitary lines were identified; staff will televise lines, scope repairs with contractor Robinson, and schedule further lining work.
Get email alerts on the Sewer Rehab topic
No spam. Unsubscribe anytime.
Superintendent Newton and staff told the board that smoke testing in Basin 4 uncovered 102 defects, including storm inlets improperly connected to the sanitary system and open or private manhole covers that allow infiltration.
"A 102 defects found," Newton said, summarizing the smoke-test results. Staff shared stills from inspection video that show groundwater entering sewer lines through seams and cracks; Newton said contractors are making good progress and that the next step is a final Robinson report to define repair scopes for Basin 9 and then Basin 4.
The board discussed likely repair approaches, including detaching storm inlets from sanitary piping and requiring some private property corrections. Staff said a contractor is lined up to televise Basin 4 and then perform repairs where needed. The work is intended to reduce I&I and lower unnecessary flow to the wastewater treatment plant.
Members asked for access to videos and reports; staff said they will share clips and the final report with the board when available.