Judge and mayor urge accelerated replacement after environmental tests at juvenile court; commission asks for full reports
Summary
Juvenile court leaders told commissioners recent environmental sampling detected mold spores, possible asbestos and lead paint in the 96‑year‑old county courthouse complex and asked the county to accelerate a replacement rather than pursue further renovations; the mayor pledged to coordinate a plan and commissioners requested the full consultant report before further action.
Get email alerts on the Public Facilities topic
No spam. Unsubscribe anytime.
Juvenile Court leaders and the county mayor told commissioners they need an expedited plan to replace the countys aging juvenile court building after preliminary environmental testing flagged airborne mold spores, lead‑based paint and possible asbestos fibers.
Judge Tarrick Sugarman said a June environmental contractor’s sampling showed elevated airborne mold spores and that some airborne particulates could yield mycotoxins. "Most things that old develop leaks…they're 96 years old," he said, adding that repeated system failures and persistent water intrusion make renovation fiscally impractical and pose continuing health and operational risks. Deputy court officials told the committee they had been temporarily displaced from some offices after visible mold growth.
Mayor Lee Harris told the committee his office will work with the juvenile court, county legal and finance staff and Facilities Management to present an accelerated funding and replacement plan. "If the commission wants us to prioritize this project and see if we can bring forward a plan ... we will work with all stakeholders to do that," the mayor said.
Commissioners expressed sharp concern about the health implications and legal exposure from damaged records and environmental hazards. Multiple members who toured the facility described damaged ceilings over file storage and recurring elevator failures that undermine public access and safety. The court said the contractor has submitted preliminary summaries and that full laboratory results (TEM analysis and water tests) are expected next week; staff promised to circulate the full environmental report to commissioners.
The committee voted to refer the request and asked Facilities Management to attend the next meeting to answer technical and cost questions. Several commissioners urged immediate interim measures to protect staff and records while a replacement plan is developed.