Council hears updates on sidewalks, trail connector, demolition and utility conflicts
Summary
Staff updated the council on multiple infrastructure projects including right-of-way and utility conflicts for a sidewalk at 9th & Blake, the Edwardsville connector trail, demolition of a house near 110th & I-70 (asbestos removal completed; estimated cost ~$30,000), and a projected project timeline with a September target for certain work.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City staff provided updates on several infrastructure and public-works projects, including sidewalk and trail work, utility relocation conflicts and demolition of a distressed property.
On the Edwardsville connector and sidewalk projects staff described utility conflicts (a large Spectrum communication box at the northwest corner of 9th & Blake), potential private-meter relocation costs that the city may have to pay, and coordination needs with AT&T and other utility companies. Staff said some sidewalk work is being deferred to align with other construction and to avoid damage from deliveries.
Staff also reported the demolition of a house near 110th & I-70 is moving forward: asbestos removal was recently finished and the demolition cost was described as “30-ish thousand” dollars. On the connector project staff noted the pedestrian bridge and other elements substantially increase project cost and that some components may push into next year, with staff citing a September target as an anticipated end date for certain phases.
Council asked for follow-up on meter relocations, easement details and the sequencing to minimize cost; staff agreed to provide further measurement details and cost estimates.