City reports progress on RORO water project; on track for pressure testing
Summary
City staff reported the RORO project has progressed: the generator arrived, electrical work remains, and pressure testing is planned; staff said the project should finish well before the Feb. 27 target date if no setbacks occur.
Get email alerts on the Water Systems topic
No spam. Unsubscribe anytime.
Staff updated the council on the RORO (water) project, reporting that equipment delivery and electrical work are nearly complete and pressure testing is imminent.
The speaker said the generator set has arrived, wiring work remains, and the company will begin pressure testing in the units. Staff expressed optimism that the project will be completed well before the February 27 finish date unless an unexpected problem arises.
Council members reacted positively to the progress report and thanked staff for the update.