City outlines pool repairs; reopening targeted for Summer 2027 if no further issues
Summary
City Administrator Beverly Hicks told the council the main pool has leaks in a return drain and the waterpark bubbler; repairs will require concrete removal and a tentative timeline targets reopening by Summer 2027 if no additional problems arise.
Get email alerts on the Recreation Infrastructure topic
No spam. Unsubscribe anytime.
City Administrator Beverly Hicks updated the council on the city pool, reporting leaks in the return drain for the main pool and problems with the waterpark bubbler.
Hicks described the required repair work, which will include removal of concrete to access piping and make repairs. She said, given there are no further issues, the pool should be ready to reopen for the Summer 2027 season. No contract award, funding appropriation or firm construction schedule was approved at the meeting.