Selectboard hears July update on Archertown Road bridge work, NHDOT approves $3,800 signage change order
Summary
Contractors poured the NW wing wall July 3 for the Archertown Road bridge over Jacobs Brook; machinery will move July 10, cofferdam and buttress deconstruction scheduled, knotweed eradication set to begin July 13, and NHDOT approved change order #3 for $3,800 to add campground signage.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Kevin Follensbee updated the Selectboard on progress for the Archertown Road bridge over Jacobs Brook. The NW wing wall was poured July 3; contractors plan to move machinery on July 10, construct a cofferdam, and deconstruct buttresses before starting knotweed eradication on July 13.
Follensbee said NHDOT approved change order #3 to add additional signage to better identify access to the nearby campground, at a cost of $3,800. The board received this as an informational update; no Selectboard motion or vote regarding the change order was recorded in the minutes.