Summary

Public works staff reported fine grading for Humboldt's sewer/street project should finish the week of Sept. 8, with asphalt paving slated for the week of Sept. 15. Sump pump inspections at the sewer/branch site were also discussed.

Jon Fischer provided the board with a status update on the ongoing sewer and street project, saying fine grading should be completed this week at both locations and that asphalt would be laid the week of Sept. 15.