Leiser Excavating granted three-week demolition extension due to weather

City of Madison Council · July 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Madison council approved a three-week extension for Leiser Excavating’s demolition work because of weather-related delays; the motion passed 4-0 after the contractor requested more time during open forum.

At the July 6 meeting of the City of Madison council, contractor Luke Leiser asked the council for more time to complete demolition work. The council agreed to a three-week extension on the demolitions, with Chair Daryl May making the motion and Councilmember Evan Casey seconding; the motion carried 4-0.

Council recorded the extension as a single, time-limited accommodation tied to weather delays. No additional conditions or fees were noted in the minutes. The extension was approved during the meeting’s open forum and entered into the minutes as an official council action.