Summary

Three bids were received for the Franklin Bottoms Bridge 39 project. Temple and Temple submitted the low bid ($718,225); commissioners accepted bids for review on Oct. 7 and later accepted the low bid on Oct. 21.

Three bids for the Bridge 39 replacement at Franklin Bottoms were submitted to the auditor's office: Temple and Temple ($718,225.00), R L Vuckson ($898,000.00), and KLB Excavating ($869,850.00). Superintendent Voyles recommended accepting the bids for review on Oct. 7; the board accepted the bids for review at that meeting.

On Oct. 21 Superintendent Voyles again recommended awarding the project to the lowest bidder, Temple and Temple, whose bid of $718,225 was the lowest of the three. Commissioner Cardwell moved to accept the lowest bid and Commissioner Ewen seconded; the motion passed.

The transcript does not record contract execution details, a construction schedule, or any performance bonds; those items were not specified at the October meetings.