Board approves $191,917.34 pay request and $15,361.59 change order for Phase III water and sewer project
Summary
Humboldt approved Stockwell Engineers' pay request #12 for $191,917.34 and change order #3 for $15,361.59 for the Phase III water and sewer project; project representative Jon Fischer said the work should conclude by the end of August.
Get email alerts on the Water And Sewer topic
No spam. Unsubscribe anytime.
The Humboldt City Board approved pay request #12 from Stockwell Engineers in the amount of $191,917.34 and approved change order #3 for $15,361.59 for the Phase III water and sewer project (motions by Julien Gambs and Theresa Muth; roll call: all present voting aye).
Jon Fischer, present to give an update on the project, indicated that the Phase III work should conclude by the end of August. The minutes do not list outstanding deficiencies or a revised completion checklist; the pay request and change order were accepted as presented and recorded in the board’s claims and action items.