Commissioners weigh $305K repair versus $1.2M replacement for bridge 4084
Summary
County staff outlined repair estimates for bridge 4084 at about $305,000 and a full concrete box replacement at roughly $1.2 million. Commissioners discussed alternatives (aluminized CMP, Duramax pipe), potential weight restrictions, and whether to seek additional state bridge funds or apply via a new $1M-per-county program with a 25% match.
Get email alerts on the Bridge Infrastructure topic
No spam. Unsubscribe anytime.
Engineering staff presented multiple options for bridge 4084 after noting the site's extreme skew makes replacement more expensive. "Concrete double-cell culvert, that length is 1,200,000," Speaker 4 said as staff detailed replacement and alternate pipe options (aluminized CMP, Duramax/HDPE with steel spiral).
Staff said the board could proceed with the MDT-approved repairs (timber pile-cap replacements and encasements) for roughly $305,000 as a shorter-term solution and limit allowable loads on the structure. Commissioners discussed whether to request additional MDT funding or pair the project with other eligible projects to improve chances under a state bridge funding opportunity that allows up to $1,000,000 per county with a 25% match.