Committee hears progress on Manchester Library air-quality tests; roof replacement estimate $613,000
Summary
Coffee County maintenance staff said air-quality testing at the Manchester Library produced mixed results — one vendor passed, another failed due to air-handler contamination — and recommended deep cleaning and retesting; staff also presented a budgetary estimate of $613,000 for a roof replacement and deferred final action until next month.
Get email alerts on the Manchester Library topic
No spam. Unsubscribe anytime.
Maintenance staff told the Capital Outlay Committee on June 4 that two environmental firms tested indoor air quality at the Manchester Library; one test passed while the other failed because of dirty air handlers. "We had it tested by two environmental companies. We passed one of them and the other one did not pass," the maintenance speaker said, noting the failed result was tied to the air handlers and that crews would take the units apart for a deep clean and schedule retesting.
Committee members discussed timing and access for the cleaning and retesting; maintenance said the cleaning work could be done quickly and hoped testing would occur "hopefully by tomorrow" with further checks next week. On the question of a roof replacement, maintenance provided a budgetary figure of $613,000 and said the committee could bid the project out; staff noted savings from the Justice Center roof procurement left potential funds that could be applied to library work if approved.
Members agreed to defer a final decision on the Manchester Library roof until next month to gather more information and prepare formal bids. Maintenance said the Justice Center roofing project will free up some budget room because it came in under its original estimate.