Abernathy bridge update: contractor performance flagged, schedule and extra funding needs assessed

Oregon Transportation Commission · June 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

ODOT project managers reported 78% completion of current work at the Abernathy/I‑205 bridge, accepted a contractor translation plan for October 2026 but noted a contractor performance score of −36 that requires corrective actions; staff outlined a near‑term $25M request to cover construction engineering, fuel escalation and owner's representative costs and estimated ground‑improvement work at $100–130M.

ODOT regional and project managers presented a detailed construction update for the Abernathy/I‑205 bridge. Vidal Francis (project area manager) said the project is about 78% complete on the current pay estimate and that the contractor's translation plan—required to widen the main span—was submitted and accepted; translation is tentatively scheduled for October 2026. "The contractor's monitored performance…resulted in a negative score…a negative 36," Francis said, triggering mandatory corrective action plans.

Travis Brower (deputy director for delivery) told commissioners the agency expects additional near‑term expenditures averaging about $1.5 million per month for construction engineering through the extended period and recommended seeking roughly $25 million now to cover inspection, a fuel escalation allowance (about $1.5M) and owner's representative costs already incurred ($2.5M). Staff also reported a preliminary estimate of $100–130 million to complete required ground improvements for seismic resiliency and said they will return with a refined finance plan and programming request.